Gas instalation cogeneration line. 4 lines of regulation and metering for 2 gas turbines.
Location:
Ain Beni Mathar (Morocco)
Design flow:
130.000 Nm³/h
Maximum pressure supply:
80 bar
Company:
Global 3 Combi
Activity:
Power Combined Cycle "Peaker" Plant
Description:
Gas instalation cogeneration line. 2 lines of regulation and metering for 4 gas turbines and 2 regulation and metering lines for heat-recovery boilers.
Location:
Escatrón, Zaragoza (Spain)
Design flow:
60.000 Nm³/h
Maximum pressure supply:
72 bar
Company:
Utisa Tableros del Mediterráneo
Activity:
Conglomerated board manufacturing
Description:
Gas instalation cogeneration line. 2 lines of regulation and metering for a gas turbine and 2 regulation and metering lines for others uses in middle pressure.
Location:
Cella, Teruel (Spain)
Design flow:
13.000 Nm³/h
Maximum pressure supply:
72 bar
Company:
Tarragona Power
Activity:
Combined cycle
Description:
Regulation, metering and postheating gas line instalation for feeding a gas turbine
Location:
Tarragona (Spain)
Design flow:
100.000 Nm³/h
Maximum pressure supply:
72 bar
Company:
S.C.A. Hygiene Paper
Activity:
Paper-mill
Description:
Gas instalation: 2 cogeneration lines. 2 regulation and metering lines
Location:
Puigpelat, Tarragona (Spain)
Design flow:
15.000 Nm³/h
Maximum pressure supply:
49,5 bar
Company:
Europac S.A.
Activity:
Paper-mill
Description:
Gas instalation: 2 cogeneration lines. 2 regulation and metering lines for 2 gas turbines and 2 regulation and metering lines for 2 heat-recovery boilers